BP Sunbury Laboratory facilities Switchboard Replacement. On Behalf of ECO of London, CB Services carried out the replacement of the existing 1200 amp switchboard which was of age where it was unsupportable and non-compliant. We were responsible for design development, installation and commissioning of the new 1200 amp supply LV switchboard.The programme was 7 Days.
The works included the following:
Intrusive site surveys to include electrical testing to all sub main circuits supplied from the existing switch panel